WP: Hammock Task

How to create a task (say Task C) in Microsoft Project 2013, where the start is influence by Task A, and Finish at the same time as Task B?

1) Create Task A & Task B, manage duration and all data needed as per normal
2) Create Task C

  • For Task C Start Date: copy ‘Finish Date’ of Task A, paste to Task C using right click – Paste Special – select Paste Link.
  • For Task C Finish Date: copy ‘Finish Date’ of Task B, paste to Task C using right click – Paste Special – select Paste Link.
#Paste Link will ensure that the task will follow other’s tasks changes.